Mayor: Stephens Street sewer work, followed by paving there and elsewhere, is to be done in time for festival

Street paving on and near Stephens Street, following storm-sewer work on the street, is expected to be completed by Sept. 20, just in time for the Midway Fall Festival, Mayor Grayson Vandegrift said in an email this morning. He gave this schedule:
  • 8/26-9/1: Storm sewer pipe work on East Stephens Street
  • 9/2-9/9: Concrete curb work on North Winter Street (near City Hall) and E. Stephens
  • 9/10-9/13: Milling and paving on E. and W. Stephens, Starks Alley, N. Winter (near 421)
  • 9/13-9/20: Clean up and finish
"This is obviously tentative," the mayor wrote. "Weather and unforeseen circumstances could delay this schedule, but this should be wrapped up by Fall Festival," which will be held Sept. 21-22. "Each of these areas is going to be much improved with more functional storm sewers, better storm-water flow, and better roadways."

Vandegrift said workers ruptured a gas line last Friday "due to the 'spaghetti' nature of lines that were buried a long long time ago without adequate mapping. That is all fixed up now, though, and the project is off to an otherwise smooth start. I’ll keep you apprised if anything changes or new developments occur."